Trafford councillors approved the Carrington Relief Road by seven votes to six. Main building starts in March 2029 and the council expects it finished in 2032.

The Carrington Relief Road has planning permission in principle. Trafford Council’s planning committee approved it by seven votes to six, the council said on 6 November (Trafford Council).

The committee met on the evening of Thursday 5 November. Officers had recommended approval, as we reported before the meeting.

The council now says the road will be finished in 2032. That is two years later than the 2030 opening year modelled in the officers’ report.

The timetable

The council’s announcement sets out three stages:

  • 2027 and 2028: preliminary works
  • March 2029: main construction starts
  • 2032: the road is complete

What has been approved

The road runs for 2.7 miles. It joins the A6144 Manchester Road in Carrington, to the west, with the Carrington Spur in Sale, to the east. Sale is about three miles north of Altrincham.

Over much of its length, the council says, it will have:

  • 7.3 metres of carriageway for traffic
  • 10 metres of width for walking and cycling, with lighting

The application is 118033/FUL/25. The council is both the applicant and the planning authority.

The planning register still listed it as “Awaiting decision” when we checked on 11 November. A formal decision notice, with its conditions, has not yet been issued (Trafford planning register).

What the council says it is for

The road is meant to take traffic off the A6144 through Carrington village. It is also the first piece of New Carrington, the allocation in the Places for Everyone plan. That allocation provides for 5,000 homes and 350,000 square metres of employment floorspace.

Cllr Liz Patel, the council’s Executive Member for Economy and Regeneration, said: “The Council has been committed to improving links to Partington for decades. This route will make that commitment a reality.”

She said it would “relieve the village of Carrington from heavy goods vehicles”.

The opposition before the vote

The papers put to councillors on the night show how contested the scheme was (additional information report).

Since the main report was published, the committee had received:

  • a petition with 1,250 names and addresses, some duplicated
  • a second petition from Transport Action Network, billed as 1,249 signatures, asking the council to weigh the “Community Alternative Option” fairly
  • a question from Cllr Duncan asking the committee to defer until it had the latest environmental evidence, updated costs and an assessment of that alternative

Officers said the second petition appeared to include 1,119 names. They said the community alternative was similar to a route the council had already discounted, and did not meet the requirements set for the road.

The officers’ main report had already recorded more than 680 objection letters in the first round of consultation and 191 in the second, against two in support.

Lorraine Eagling of the Friends of Carrington Moss and Cllr Waterworth were listed to speak against. Cllr Patel spoke for the applicant. Cllrs Cosby and Wright sent a joint written statement in favour.

The chemical works

CTO Polyolefins, whose Carrington plant is a major accident hazard site, kept its objection to the end (addendum report). The western half of the road follows the private A1 Road through its site.

The council, as applicant, answered that the safety work needed is secured by planning conditions. It accepted that buying the land and settling compensation are still to be resolved, and said permission does not override the company’s property rights.

The conditions put to councillors include one that stops any work until a scheme protecting CTO’s operations, including access to its main site and outlying assets, has been approved. Officers also noted that a contract for the works to rationalise the plant’s equipment along the route had already been let.

What it means for you

If you use the A6144 between Sale, Carrington and Partington, nothing changes yet. Preliminary work is not due until 2027, and main building until March 2029.

When it opens, the council says, Partington and Sale will be linked by a lit walking and cycling route as well as the new road.

The vote was close. The land is still to be bought, and the formal decision notice is still to come. We will report when it is issued.